}); }); ]).push({}); }); Jkaf India By Pushpendra Kumar: July 2021

Saturday, 10 July 2021

Geotechnical investigation or Soil investigation for Highway project in Hilly terrain

 

A  note on Geo-technical Investigation in Soil and Rock For a Highway Project in Hilly area By - Pushpendra Kumar, Deputy Manager, Geology, Rodic Consultants PVt. Ltd.


Sub-Surface investigation/Geo-technical instigation/ Soil investigation is play a very important role for a Highway project especially in a Hilly terrain like Himalayas. It directly affected to cost of project as well as completion time very badly if not executed as per standard. As we know, based on the preliminary instigation we have finalized our project design and expected cost with a time duration of the project. These details may be updated during detailed investigation later. I f  there is  major change is observed during details Geo-technical investigation then all the things will be change sometimes as design, project cost and the project time  schedule.  So it is suggested not to omit any sequences of investigation as generally observered and planning of investigation at different stage ( desk planning preliminary/reconnaissance, details survey, type of field test required and sample selection etc) must be prepared by a well experience expert.  “Without a Geo-technical investigation, ground is a hazard especially in hilly terrain. You pay for geotechnical investigation or will pay for delay or design up gradation of project during execution.

During Geo-technical investigation correct Rock core logging and interpretation is very important during core drilling activity. It must be ensured that maximum information should be recorded during core drilling activity. During core drilling activity final log must be included following information such as-

       Project Name

       Borehole number

       Location and orientation of borehole

       Drilling technique

       Drillers daily record

       Flush returns

       Standing water levels

       Litho-Unit

       SPT no. In soft strata etc.

       Sub-surface investigation not just a core drilling but also  includes pit excavation core drilling with cone penetration test, field shear test, dilatometer test, permeability test etc. as required by project and design team. It will also include collection and preservation of soil/rock sample (disturb and undisturbed) from bore hole borrow pit etc. Except SPT and CPT all other test will be conducted on samples in laboratory by following IS and IRC standard.

       Depth and numbers of Bore hole taken.


Soil investigation
Geo-technical Investigation depth for Structure



Geo-technical investigation  depth for Tunnel
Depth of geo-technical investigation for Slide area


Depth of geotechnical investigation for Tunnel area

       The depth of Bore hole for structure must be 1.5 times of the width of foundation below foundation level or if RQD encountered >80% continuously up to 3 meters. If suitable soil not encountered it can increase up to 4 times. For embankment and guide bund depth must be 2.4 times of height but not less than 20 m. For landslide the investigation depth should below 5-10 m from slip circle or failure plane. In tunnel area depth of the investigation must achieved up to 5-10 meters below invert level.


       At least 1 no. of bore hole taken for each foundation of Structure. One bore hole must be taken for approaches at both side of bridge/viaduct at 50-100 meters from abutment location. If any complication observed in lithology transverse bore hole may taken to know the variation in underlying strata

     A soft clayey strata must be investigated carefully and shall be mentioned specially as it generally create problem during execution state in highway, structures as well as in tunnels.

       During investigation all required data must be recorded as mentioned in IS:5313 and IS:4464. The samples must be stored as per IS:4078.

       The core recovery must be classified according to Cl. 2405.6, very poor to excellent rock mass.

       In-situ test for deformation shale be conducted in field as per IS:7292,7317,7746, 1888 etc.

 

Rock cores and split spoon samples are known as undisturbed sample.

For details how sample taken may referred IRC:75.

The size required sample is given in table 2400-2. The length of core sample must be 150-200 mm for 40 mm dia core and 300 mm for 100 dia core.

In Hilly terrain it is mandatory to taken bore hole for Hill slope excavation and stabilization works. It can be decided based on cut slope height, strata, and ground water condition.

If slide area exist in a project, one bore hole shale be taken for each slide area. Other necessary investigation may be carried out as suggested by expert.

 

For tunneling, seismic refraction and electric resistivity survey shall be conducted with detailed core drilling to maximize in-situ (underground) information at tunnel area. It is very helpful for design stage as well as construction stage. Field shear test must be conducted to validate lab test result for c and phi parameters. Dilatometer test also be carried in bore hole  for modulus of deformation of  rock mass

 

Few Important IS code which is helpful other than MoRTH-2400 during Geotechnical investigation:

 

IS:1494, IS:1888, IS:1892,IS:2131,IS:2132

IS:2720, IS:3720, IS:4464, IS4434, IS:4453

IS:4968, IS:5313, IS:4079, IS:7292,IS:7317

IS:1892,1979

IS:7746

IRC:78 and IRC:75 

IRC-SP-91,2010

IRC:SP:48, 1998

 

You may contact me via mail or my blog.